Press release
GENESEE COUNTY, NY – The Genesee County Highway Department is announcing the commencement
of the first round of NOVA Chip Paving on Monday, June 3rd. This project will enhance road surfaces
across several vital routes, improving driving conditions and extending the life of local roadways.
Schedule and Locations:
- Perry Road (Pavilion/LeRoy):
o June 3rd – 4th: Route 20 to Route 19
o June 5th – 6th: Route 20 to Route 63 - Linden Road (Bethany):
o June 10th – 11th: Bethany Center/Linden intersection to Silver/Linden intersection - Brookville Road (Alexander):
o June 12th – 13th: Brookville/Creek intersection to Brookville/Route 20 intersection - Dodgeson Rd/Bennett Rd/Simonds Rd/Sumner Rd (Darien):
o June 17th – 20th: Dodgeson/Halstead intersection to Sumner/Harper intersection
Weather permitting, the entire project is expected to be completed by June 20th.
Road Closures and Access:
During work hours (Monday through Thursday, 6:00 AM to 4:00 PM), the affected roads will be closed to
through traffic. Emergency responders will be able to pass through the work zones as needed. Local
schools, including Le Roy School, Pavilion School, Alexander School, and Pembroke School, have been
notified to ensure school buses can still pick up and drop off students without disruption. Adjustments
will be made to accommodate school transportation needs.
Residents and commuters are advised to plan alternate routes during this period.