BATAVIA/City of Batavia air header project nearly complete, odor will disappear over the next week

Press release

Project nears completion


BATAVIA, NY – A Million dollar capital project to replace the air header system at the Waste Water
Treatment Plant (WWTP) is nearly complete. This morning the air delivery system was placed back in
service for all three ponds serviced by the line.

Over the next week, we are hopeful that there will be marked improvements of odors coming from the
Waste Water Treatment Plant as the ponds recover from the previously compromised air supply.

The City advanced the project to the top of the capital improvement list for 2021, but supply chain delays
delayed the project by about two months. Upon material delivery, Keeler Construction Company of
Albion, NY, worked an accelerated schedule to get the system back in service. Other than the incidental,
restoration the project is substantially complete.

Flows from users with heavy constituents will be added back into the system gradually over the next few
weeks to ensure that there is not a major impact on the system.

31 year old pipe removed(submitted photo)
Newly installed pipe with corrosion resistant wrap and high temperature gaskets(submitted photo)
New pipeline being connected to the air compressors(submitted photo)

Leave a Reply

Your email address will not be published. Required fields are marked *