Power and Construction Group crews are scheduled to begin work on the night of July 18th, 2022 for the NYPA-City of Batavia LED Street Light Project.
The tentative schedule is as follows:
Monday & Tuesday – start/finish Main Street and then start Oak Street.
Tuesday & Wednesday – finish Oak Street and then start Ellicott Street/Route 63.
Wednesday through Friday – finish Ellicott Street/Route 63 and all other cobrahead street light locations.
Traffic delays should be expected; however, no street closures are anticipated at this time.